Location:
Riverside, CA
Owner:
County of Riverside
General Contractor:
W.B. Allen Construction, Inc.
Contract:
$320,000
Completed:
May 2003
Summary:
Project duration was 7 months and consisted of converting the old basement storage into a new
multi-purpose hall for meetings, conventions and banquets.
This was a design/build project for Chism, which included replacing the basement chiller with a new
250 ton Carrier HXC Screw, replacing the cooling tower, adding two 20 ton air handlers, a boiler,
DDC controls and ductwork, along with chilled and hot water piping.